Content
IT Integration Standardization Phase
IT Integration Process Enablement Phase
Progress - Task Group
IT Integration Phases
IT Integration Punch List
Overall Progress
STANDARDIZATION PHASE (1 – 90 DAYS)
Coverage
Infrastructure Improvement Phase 1 competed, Phase 2 starting 3 offices Email Migration tested and piloted; staged pending business approval (bids)
Schedule
Email pushed to begin after May 30 due to heavy bid schedule
PROCESS ENABLEMENT PHASE (90 – 180 DAYS)
Coverage
ERP Migration kicked off; planning session with all players in Arkansas
Bid users identified with business analysis underway
Schedule
ERP Planning May 15 – 16; Go live October 1
Area: Acquirer Connectivity
Issues:
- Carry over-Email cleanup
- Carry over- AD coverage
Mitigation:
- Email complete by 6/20
- AD kicked off 6/17
Area: Acquirer Infrastructure
Issues:
- DR site shutdown
- Carry over-Final improvements
Mitigation:
- Site shutdown initiated
- Ohio scheduled
Area: IT Team Development
Issues:
- Depth and strength to work with Acquirer IT
- Availability to focus on business
Mitigation:
- Moved FTE to Chicago; engaged temp
- Improvements reduce future risk...